US & World

A small bat puts Kibosch in a power line logging for two months

Portland, Maine (AP) — Logging in key parts of power lines in western Maine ceases as soon as it begins to protect newborn bats protected by the federal government.

New England Clean Energy Connect has a narrow window of just two weeks to get started after the Federal Court of Appeals issued a green light to continue last week. Northern long-eared bat puppies are born, and tree removal should be stopped in June and July, when they are still flightless.

A permit issued by the Army Corps of Engineers in November banned logging in June and July, and tree crew members already at work were suspended for two months to protect declining bats. I was planning to do it. Due to so-called white nose syndrome.

“NECEC Transmission LLC has been aware of and will comply with this prohibition since the start of the federal consultation and licensing process,” NECEC said in a statement.

The long-eared bats in the north are small (the size of a small rat) and live in trees rather than in caves.

Nate Webb, director of wildlife at Maine’s Inland Fisheries Department, said bats were threatened by the federal government and extinct by the state government due to Whitenose Syndrome, which killed 90% to 95% of all bats in Maine. It is stated that it is at stake. And wildlife.

The $ 1 billion New England Clean Energy Connect aims to serve as a conduit for up to 1,200 MW of electricity from Canada’s hydropower projects to reach the New England power grid.

Many of the projects follow existing utility tunnels, but a new section that opens up 53 miles (85 km) of forest will be subject to proceedings and referendums in November.

Last week, the First US Court of Appeals rejected a request by an environmental group to postpone construction, allowing workers to move on to new plots in the woodlands of western Maine. Three environmental groups have sued the US Army Corps of Engineers for a more detailed environmental review.

However, a court decision allowed the company to work for only two weeks before the bats were suspended.

Logging will be suspended in June and July, but other construction, including the installation of poles, could proceed, officials said. According to the U.S. Army Corps of Engineers permit, logging should be done “to the maximum extent practicable” between October 16th and April 19th, but logging at other times Not banned.

Thorndickinson, President and CEO of NECEC, said:

If the proceedings and potential referendum do not delay or upset it, the project will be fully funded by Massachusetts toll payers to achieve the Massachusetts Clean Energy Goal.

Proponents say power lines have the effect of reducing energy prices across the region, in addition to reducing greenhouse gas emissions. Critics, meanwhile, say the environmental benefits are exaggerated, destroying forests and harming wildlife.

The project was previously approved by the Maine Environmental Protection Agency, the Maine Land Use Planning Commission, and the Maine Public Utility Commission.

The second referendum on the project is pending action in the state legislature. The first referendum was thrown by the Maine Supreme Court for constitutional reasons.

A small bat puts Kibosch in a power line logging for two months

Source link A small bat puts Kibosch in a power line logging for two months

Related Articles

Back to top button